Wed:
8/25/99 Tour of campus
monuments and fountain area,
(photography, sketches, interviews, area montage)
Friday: 8/27/99
Meet clients
(have prepared questions, notes taking)
Monday: 8/30/99
Site Analysis: (1) physical features; (existing
natural, artificial, historical)
(2) utilities; electric, water, drainage, etc.
(3) human use patterns, daily, events, etc.
(4) environmental features, (wind, sun,
temp., rain, etc.
SitePlan(1/8"=l'-O"): significant features,all directions
Wed:
9/1/99 Three (3)
schematic options @ 1/8"=l'-O"; chipboard
models; 12Xl8 sketches; text to supplement
Friday: 9/3/99
Cross section of design option with OMS and
Field house
Monday: 9/6/99
Revised scheme with 1/2" cardboard model
(meet with clients, show development work and
scheme)
Wed: 9/8/99 Revisions development
Friday 9/10/99
last crit: Revised scheme as per comments and new
directions
Monday 9/13/99 work session
Wed. 9/15/99 final drawings and model work due
Friday 9/17/99 all work submitted for client review
Final submission requirements: on 20X30" foam core board(s)
- model foam core
- site plan
- plan
- site section
- section
- (3)vignettes, critical perspectives (slides or form*Z model)