The construction of a house for a low income resident.
Site Activity
04/09/01 ....Finishing
03/30/01 ....Grass
03/02/01 ....Finishing
02/07/01 ....Drive and Tile
01/31/01 ....Siding Complete
01/24/01 ....Siding
12/20/00 ....Cabinets and Stain
12/11/00 ....Cabinets and Paint
12/01/00 ....Doors and Cabinets
11/21/00 ....Tape and Float
11/13/00 ....Drywall
11/03/00 ....Insulation
10/27/00 ....Framing Final
10/20/00 ....Roofing Starts
10/11/00 ....Framing Continues
10/04/00 ....Framing
09/29/00 ....Roof Framing
09/27/00 ....Framing
09/25/00 ....Framing
09/21/00 ....Wall Tilt-up
09/18/00 ....Slab Prep