| 04/09/01 | ....Finishing |
| 03/30/01 | ....Grass |
| 03/02/01 | ....Finishing |
| 02/07/01 | ....Drive and Tile |
| 01/31/01 | ....Siding Complete |
| 01/24/01 | ....Siding |
| 12/20/00 | ....Cabinets and Stain |
| 12/11/00 | ....Cabinets and Paint |
| 12/01/00 | ....Doors and Cabinets |
| 11/21/00 | ....Tape and Float |
| 11/13/00 | ....Drywall |
| 11/03/00 | ....Insulation |
| 10/27/00 | ....Framing Final |
| 10/20/00 | ....Roofing Starts |
| 10/11/00 | ....Framing Continues |
| 10/04/00 | ....Framing |
| 09/29/00 | ....Roof Framing |
| 09/27/00 | ....Framing |
| 09/25/00 | ....Framing |
| 09/21/00 | ....Wall Tilt-up |
| 09/18/00 | ....Slab Prep |