Community Action Project A Building Addition for Health for Friends. |
| 12/18/01 | ....Student Project Photographs |
| 12/17/01 | ....Christmas Break Sets In |
| 11/30/01 | ....Attic Fire Wall |
| 11/28/01 | ....Door Lock |
| 11/26/01 | ....Interior Work |
| 11/25/01 | ....Norman Transcript Article |
| 11/16/01 | ....Interior Continues |
| 11/09/01 | ....Entrance Roof |
| 11/07/01 | ....Entrance Continues |
| 11/05/01 | ....Entrance Start |
| 10/31/01 | ....Interior Continues |
| 10/25/01 | ....Steel Studs Continue |
| 10/23/01 | ....Steel Studs |
| 10/17/01 | ....Column Footing |
| 10/15/01 | ....Ceiling Drywall |
| 10/12/01 | ....Rough-In |
| 10/08/01 | ....Ceiling Drywall Arrives |
| 10/05/01 | ....Rough-In |
| 10/02/01 | ....Electrical Rough-In |
| 09/30/01 | ....Interior Layout |
| 09/26/01 | ....Roofing |
| 09/25/01 | ....Roofing |
| 09/24/01 | ....Roof |
| 09/23/01 | ....Roof |
| 09/20/01 | ....Trusses&Deck |
| 09/19/01 | ....Trusses |
| 09/18/01 | ....Trusses |
| 09/17/01 | ....Trusses |
| 09/16/01 | ....Trusses |
| 09/13/01 | ....Walls |
| 09/12/01 | ....First Walls |
| 09/09/01 | ....Wall Layout |
| 09/07/01 | ....Slab Pour |
| 09/06/01 | ....Slab Prep |
| 09/04/01 | ....Slab Prep |
| 08/31/01 | ....Stem Wall |
| 08/30/01 | ....Footing |
| 08/29/01 | ....Oklahoman Article |
| 08/27/01 | ....Pre-Construction Meeting |
| 08/27/01 | ....Norman Transcript Article |
| 08/27/01 | ....Oklahoma Daily Article |