Community Action Project The construction of a house for a low income resident. |
| 01/30/98 | ....Finishing Touches |
| 12/17/97 | ....Tile |
| 12/15/97 | ....Paint and Clean Up |
| 12/11/97 | ....Interior Paint |
| 12/08/97 | ....Interior Trim |
| 12/04/97 | ....Drywall Tape and Float |
| 12/01/97 | ....Drywall and Brick Continue |
| 11/25/97 | ....Siding Finishes |
| 11/24/97 | ....Siding Progresses |
| 11/21/97 | ....Siding |
| 11/19/97 | ....Inspection and Vapor Barrier |
| 11/18/97 | ....Insulation and Siding |
| 11/10/97 | ....Interior Framing |
| 11/05/97 | ....Plumbing and Electrical |
| 11/03/97 | ....Interior Work Begins |
| 10/30/97 | ....Roofing |
| 10/22/97 | ....Roof Decking |
| 10/20/97 | ....Rafters |
| 10/14/97 | ....Porch and Carport Concrete |
| 10/13/97 | ....Framing Takes Shape |
| 10/10/97 | ....Framing Starts |
| 10/06/97 | ....Slab Preparation |
| 10/03/97 | ....Plumbing |
| 10/01/97 | ....Formwork |
| 09/26/97 | ....Site Preparation |
| 09/24/97 | ....Gound Breaking |