Community Action Project The construction of a house for a low income resident. |
| 01/26/99 | ....Carpet |
| 12/23/98 | ....Finishes Continue |
| 12/17/98 | ....Cabinet Progress |
| 12/15/98 | ....Grout and Paint |
| 12/11/98 | ....Tile and Cabinets |
| 12/09/98 | ....Finish Paint & Caulk |
| 12/05/98 | ....Paint & Trim |
| 12/01/98 | ....Trim |
| 11/23/98 | ....Drive Layout- Doors- Touch-up |
| 11/20/98 | ....Paint & Driveway Excavation |
| 11/16/98 | ....Tape & Float |
| 11/10/98 | ....Drywall Continues... |
| 11/06/98 | ....Drywall |
| 11/03/98 | ....Insulation |
| 10/27/98 | ....Siding and Interior |
| 10/23/98 | ....Siding Begins and HVAC Rough In |
| 10/20/98 | ....Roofing and Electrical Rough In |
| 10/13/98 | ....Soffit and Interior Framing |
| 10/06/98 | ....Roof Deck |
| 09/26/98 | ....Framing |
| 09/09/98 | ....Concrete Slab |