Community Action Project
The construction of a house for a low income resident.
Site Activity
01/26/99 ....Carpet
12/23/98 ....Finishes Continue
12/17/98 ....Cabinet Progress
12/15/98 ....Grout and Paint
12/11/98 ....Tile and Cabinets
12/09/98 ....Finish Paint & Caulk
12/05/98 ....Paint & Trim
12/01/98 ....Trim
11/23/98 ....Drive Layout- Doors- Touch-up
11/20/98 ....Paint & Driveway Excavation
11/16/98 ....Tape & Float
11/10/98 ....Drywall Continues...
11/06/98 ....Drywall
11/03/98 ....Insulation
10/27/98 ....Siding and Interior
10/23/98 ....Siding Begins and HVAC Rough In
10/20/98 ....Roofing and Electrical Rough In
10/13/98 ....Soffit and Interior Framing
10/06/98 ....Roof Deck
09/26/98 ....Framing
09/09/98 ....Concrete Slab


Web Page developed by Joel K. Dietrich, AIA
Copyright © 1999 Division of Architecture